Visit of the IDEAM team to the works of the viaduct over the river Serpis

Last Friday September 7th, almost half of our team visited the work of the composite (steel and concrete) Viaduct over the Serpis River in the access to the port of Gandia.

IDEAM has made the detailed design and is doing the technical assistance during execution for Copcisa, who is executing the bridge. Horta-Cosalada has been the workshop in charge of the execution of the steel structure and the property is the Ministry of Public Works.

The bridge has 4 continuous spans of 36 + 59 + 59 + 36 m with variable depth and also variable width of up to 17.60 m, and nowadays it has already executed the entire steel structure and the bottom concrete in hogging areas, and it finds in the phase of placing of the upper precast slabs and the slab reinforcement.

We want to congratulate all those involved in the execution, Contractor, Steel Workshop and Property, as well as all the IDEAM team that has participated in the detailed design and the assistance to the works, for the fantastic result that can be seen in the images. Congratulations to all.

 

https://www.youtube.com/watch?v=OZfAmJY_otg