Emergency actions of the Bridge over the Guadalfeo River. Road N-340 Salobreña, Granada. Spain
Salobreña, Granada. Spain
Spanish Ministry of Public Works
Betazul S.A.
Main inspection, Repairing Project and Technical Support

110 m
5 spans of 22.30 m
Demolition of the half lap joint. Improvement of the bearing conditions of the half-lap joint achieved cutting the old reinforcement and arranging mechanic sleeves with new reinforcement. Reinforcement of the main resisting mechanism of the bearing. Arrangement of stainless steel sheets and new bearing system. As well, other type of actions were carried out to recover the necessary safety level, functionality and durability of the structure